VerbatimParliament, as it happens

Wind Power: Planning Permission

Asked by Kirsty BlackmanScottish National PartyDepartment for Energy Security and Net ZeroTabled Answered 8 June 2026UIN 4116

The question

To ask the Secretary of State for Energy Security and Net Zero, what target timescales his Department has set for the determination of offshore wind and grid connection planning applications; and what steps he is taking to reduce delays in consenting for nationally significant energy infrastructure.

Answered by Michael Shanks

In England and Wales, the Planning Act 2008 sets statutory deadlines for the Examining Authority and the deciding Secretary of State. These do not differ by infrastructure type.

The Government is taking multiple actions to speed up the planning process including in the Planning and Infrastructure Act 2025, and in its response to the Nuclear Regulatory Review in March 2026.

Planning applications relating to the grid in Scotland are a matter for Scottish Ministers.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim