Data Centres: Energy

Asked by Chris BlooreLabourDepartment for Energy Security and Net ZeroTabled Answered 8 June 2026UIN 4762

The question

To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of the impact of energy infrastructure procurement times on the delivery timeline for nationally significant data centres.

Answered by Michael Shanks

Government recognises the impact of electricity infrastructure procurement times on data centres and is supporting supply chains and skills across industry through the Sector Growth Plan, to improve demand visibility, strengthen domestic manufacturing, and help reduce lead times and support earlier investment decisions.

This is part of a package of measures to accelerate network build and connections, including for data centres, that includes exploring direct high-voltage connections and self-build of electricity assets, reforms to manage speculative demand applications and accelerate strategically important projects including AI Growth Zones, and establishing the AI Energy Council to explore opportunities to attract investment.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim