To ask the Secretary of State for Defence, what are the repayment terms for construction and maintenance work carried out to bases used by US forces.

Answered by Luke Pollard

The Ministry of Defence (MOD) initially meets all costs for construction and maintenance work on United States Visiting Forces (USVF) projects. The timing of payments to contractors depends on the terms agreed in each contract. Once the MOD has paid the contractor invoices, it raises recharge invoices to the USVF. These recharge invoices must be settled within 60 days.

Additionally, the USVF provides a contribution equal to 7.5% of the actual construction costs towards MOD overheads. This contribution is also payable within 60 days, in line with the recharge terms for construction and maintenance expenditure.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim