Liverpool Street Station: Construction

Asked by Sir Ashley FoxConservativeDepartment for TransportTabled Answered 3 July 2026UIN 12909

The question

To ask the Secretary of State for Transport, what estimate has been made of the potential impact of the Liverpool Street Station redevelopment scheme on passenger capacity during construction, including the proportion of concourse space and platforms expected to be unavailable.

Answered by Keir Mather

Maintaining services during construction is a priority. The proposed phased approach keeps the station operational throughout. While concourse capacity will be reduced in phases during construction, passenger footfall has been modelled against this to ensure the station can remain operational and meet passenger need.

Only platforms 1-2 will close for a portion of the build to allow the mezzanine extension. Services from those platforms can be re-redirected to others to enable the works as no other platforms require closure.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim