Network Rail: Biodiversity

Asked by Joe RobertsonConservativeDepartment for TransportTabled Answered 29 June 2026UIN 13067

The question

To ask the Secretary of State for Transport, whether she has made an assessment of the potential impact of the reprioritisation of vegetation management following the identification of protected species results on costs to Network Rail.

Answered by Simon Lightwood

Network Rail has not made specific estimates of the cost or time arising from identification of protected species. For Network Rail, such activities are embedded within wider project development, environmental mitigation and vegetation management processes, rather than recorded as discrete cost categories.


Licensing and survey requirements can influence project scheduling, particularly where seasonal survey constraints apply or where mitigation measures are required before works may proceed. However, the scale of any impacts on cost or programme varies significantly depending on the nature, location and timing of individual projects, and has not been quantified centrally. Effective project planning supports with limiting the impact of these requirements on project delivery.

Network Rail will always attempt to continue work using non-licensable techniques. Where this is not possible, licences will be applied for and work undertaken according to any condition presented in a granted licence.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim