VerbatimParliament, as it happens

Network Rail: Biodiversity

Asked by Mr Richard HoldenConservativeDepartment for TransportTabled Answered 10 July 2026UIN 15006

The question

To ask the Secretary of State for Transport, pursuant to the Answer of 29 June 2026 to Question 13067 on Network Rail: Biodiversity, whether her Department plans to require Network Rail to record centrally the (a) costs and (b) delays to projects arising from protected species survey, licensing and mitigation requirements.

Answered by Simon Lightwood

The Department for Transport does not plan to require Network Rail to record centrally the costs and any delays to projects arising from protected species survey, licencing and mitigation requirements.

Network Rail must comply with species licencing requirements when delivering maintenance and enhancement projects. Network Rail has been working with Natural England to reduce the burden of species licencing through district level licences for some species.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim