VerbatimParliament, as it happens

National Grid: Wind Power

Asked by Martin WrigleyLiberal DemocratDepartment for Energy Security and Net ZeroTabled Answered 15 July 2026UIN 16698

The question

To ask the Secretary of State for Energy Security and Net Zero, what steps he is taking to increase grid capacity to enable a reduction in wind curtailment.

Answered by Michael Shanks

The current extent of grid constraints reflects years of underinvestment, with new network infrastructure development having lagged the expansion of new generation. That is why we are delivering the biggest upgrade to Great Britain’s electricity network in decades, helping bring forward capacity needed to reduce constraint costs. NESO analysis suggests that bringing forward three major transmission reinforcement projects by one year could reduce network constraint costs by around £4 billion in 2030.

Measures set out in the Reformed National Pricing Delivery Plan will further reduce constraint costs by up to £1 billion in 2030, helping lower household energy bills.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim