VerbatimParliament, as it happens

Ajax Vehicles

Asked by Chris EvansLabour (Co-op)Ministry of DefenceTabled Answered 17 July 2026UIN 16869

The question

To ask the Secretary of State for Defence, what is the estimated cost for the Ajax 2 package of upgrades.

Answered by Luke Pollard

I refer the hon. Member to the answer I gave on 22 June 2026 to Question 9411 to the hon. Member for Huntingdon (Mr Obese-Jecty):

‘Ajax 2’ is not a separate programme, but shorthand for a package of ongoing and planned enhancements to the Ajax family of vehicles. As such, there is no single projected cost for ‘Ajax 2’.

The Ajax programme itself is a £6.3 billion programme to deliver 589 vehicles to the Army, and the approval remains unchanged for the agreed scope of delivery.

I will continue to keep the House informed about developments with Ajax, as I have done since Exercise Titan Storm via Written Ministerial Statement.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →