Unmanned Air Systems
The question
To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Protector, when the a) Review Note and b) rebaselining of milestones will be completed for the Protector Programme.
Answered by Ministry of Defence
Following release of the Defence Investment Plan, a review of Protector is currently underway. Rebaselined milestones are expected by December 2026, with a Review Note to follow.