Prisons: Procurement
The question
To ask the Secretary of State for Justice, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, PFI Prison Expiry and Transfer Tranche 3, for what specific reasons has the project end date been moved from 28 January 2028 to 31 July 2029.
Answered by Ministry of Justice
The PFI Prison Expiry and Transfer Tranche 3 Project end date has moved to 31 July 2029 following a change in scope to include HMP Rye Hill. The revised date reflects the additional time required to complete the expanded scope and final project closure activities.
Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →