Water Abstraction: Teddington

Asked by Sarah OlneyLiberal DemocratDepartment for Environment, Food and Rural AffairsTabled Answered 7 September 2026UIN 26076

The question

To ask the Secretary of State for Environment, Food and Rural Affairs, pursuant to the answer provided on 14th July 2026, to Question 16496, on Water Abstraction: (a) what determination she made of the flow rate, measured at the Kingston gauge, that would trigger operation of the Teddington Direct River Abstraction Scheme, and (b) given that trigger event and based on historical river flow data, what assessment has she made of the average incremental cost per megalitre over the lifetime of the scheme.

Answered by Department for Environment, Food and Rural Affairs

The proposed Teddington Direct River Abstraction is an intermittent drought resilience scheme triggered by river flow and reservoir storage conditions through the Lower Thames Control Diagram and does not have a single flow-rate trigger at the Kingston gauge.

Thames Water's Gate 3 submission indicates operation may be triggered when naturalised flow over Teddington Weir falls to around 3,000 Ml/d on average for 10 days during a qualifying drought event, alongside relevant reservoir storage thresholds.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim