The question

To ask the Secretary of State for Energy Security and Net Zero, how many proposed data centres have (a) requested and (b) received an electricity-grid connection offer; what their combined requested capacity is; and what assessment has been made of the potential effect of those requests on connection dates for (i) housing developments, (ii) manufacturing businesses and (iii) low-carbon electricity generation.

Answered by Department for Energy Security and Net Zero

Data collected in 2025 and published by the National Energy System Operator shows 72.8 GW of capacity allocated to data centres in the GB connection queue across transmission and distribution. It is not currently possible to provide a count of individual projects.

Government recently consulted on measures to manage the current oversubscription of data centre connections, which is contributing to connection delays for demand projects of all types, and will publish its response in due course.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim